Steel Roll Pit Excavation – Hydro Excavation services were completed to create an 8’ x 8’ and 35 foot deep pit inside a warehouse for manufacturing facility. December 2019 Warren, Michigan.

Retention Pond Screening for private client – Vacuum silt & disposal until resolution achieved. Hundreds of loads over 1 month long project. July 2019 Jeddo, Michigan.

Commercial Parking Lot for Large Automotive Safety Supplier – excavation, backfill, storm sewer installation, underground detention system and sheeting for retaining walls. September 2019 Auburn Hills, Michigan

Landfill Cap – relocation of drainage ditch, strip & excavate existing cap then fill & place aggregate material to meet DEQ approval. 17 acre of seeding to complete project. Fall 2017 Saint Clair County, Michigan

Well Rehab & Access Road Construction – Site stripping, grading & restoration. Transportation of over 40,000 tons of aggregate materials. Rental equip. and other support services were also provided for improvements. 2015-2019 southeast Michigan.

MDOT Demo & Land Clearing at Neal Plaza & Harker Street – Making way for Blue Water Bridge Plaza, We demo’d 6 buildings, transported and completed total site restoration. December 2016, Port Huron, Michigan.

Construction of Sugar Beet Receiving Pad –5 freighters of aggregate used to construct the new pad & scale house. Grading, drainage expansion, land clearing and demolition were all completed on this turn-key project. Fall 2020 Croslex, Michigan.

Sanilac County Shoreline Project – 1,200 ton of anchor rock was transported from Alpena to M-25 over 3 weeks to prevent erosion along the shoreline. May 2020 Sanilac County, Michigan.

MDOT I-696 & M-5 Spill – Emergency Response to excavate, remediate and restore 10cy of contaminated soil due to a trucking accident. Fall 2019 Novi, MI.

Birch Run ER Spill – diesel fuel and oil contaminated the road median after a truck rolled. MLC responded to the site immediately to remediate and restore the 30cy of contaminated area. June 2020 Birch Run, MI.

Rig Pits – MLC HXX Division was called out to clean rig pits for a client at a natural gas well site. September 2016 Howell, MI.

Demo & Tank Pull – demolished overhead canopy and pulled 6 underground storage tanks; 12,000-18,000 gallon tanks. Remediated site for new construction. October 2018 Pontiac, MI.

Canal Road Construction – crews from ML Chartier work to tear out the existing road in preparation for a new turn lane. Summer 2019 Utica, MI.

Rig Support – Hot oil service for cleaning the tubing, Kill truck service for keeping the well dead while work was completed & Vac truck supplied brine to hot oiler used to kill the well. August, 2020 Beaverton, MI.